CHN00843: NSX Maintenance - GSP
Scheduled Maintenance Report for Green Cloud Defense
Completed
The scheduled maintenance has been completed.
Posted Oct 21, 2020 - 06:01 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 21, 2020 - 00:01 EDT
Scheduled
Green Cloud will be upgrading VMware NSX in the Greenville, SC (GSP) data center to take advantage of performance and stability enhancements. The upgrade will take place on October 21st between 12:00am and 6:00am Eastern time. The vCloud Director interface will be unavailable but virtual servers will remain connected and operational. Please let us know if you have any issues or questions at support@gogreencloud.com or 877-465-1217.
Posted Oct 19, 2020 - 16:47 EDT
This scheduled maintenance affected: IaaS (IaaS - Greenville, SC).